Completion of Quibala power substation set for June

Luanda - The mobile electrical substation, under construction in Quibala municipality, coastal Cuanza Sul province, whose works are scheduled to end next June, will help boost economic activity, especially agriculture in the region.

Send by email

To share this news by email, fill out the information below and click Send

Correct

To report errors in the texts of articles published, fill out the information below and click Send

Cuanza Sul: electrical substation

Photo: Joaquim Tomás

The construction of the infrastructure, with capacity to generate 220/30 kV - 10 Mva, started in April.

Quibala power substation will meet needs such as food conservation, lighting for homes and towns, as well as support for the business activity in the region.


A note from the sector, reached ANGOP on Saturday, quotes the minister of Energy and Water, João Baptista Borges, as having travelled to the province on Friday.

In his trip, that also covered the northern province of Cuanza Norte, aimed at assessing the progress of Quibala's electrification works.


The document also makes reference to the beginning simultaneously of the construction of  the first phase of the distribution networks in medium and low voltage.

The process includes home connections, which will regularly bring energy to the homes of the local inhabitants from the next months of July and August.


As for the expansion of the electricity network to agricultural farms, a project is underway, in partnership with the Ministry of Agriculture and Fisheries, to execute the medium voltage lines, which will have an approximate extension of 75 kilometers.

The objective is to ensure sustainable development of agriculture, taking advantage of the existing availability of hydroelectric energy from the national electricity grid.
 

Tags Energia  

Read also
  • 21/05/2020 08:12:15

    Minister wants improved revenue collection mechanism

    Luanda - Angolan minister of Energy and Water João Baptista Borges Wednesday urged the sector's companies to improve revenue collection mechanisms to contribute to the country's development process and ensure its sustainability.

  • 20/03/2020 15:03:47

    Chinese firm to invest over $20 million in electricity meters

    Luanda - The Chinese company Hengye Electronics Industry Ltd plans to invest more than US $20 Million in the installation of factory to make water and energy meters in the Luanda-Bengo Special Economic Zone (ZEE).

  • 06/03/2020 17:49:55

    Laúca to reach 2,070 MW production in October

    Laúca / Malanje - The Laúca Hydroelectric Power Plant will reach, by October this year, its maximum capacity of 2,070 megawatts of production, with the entry into operation of the sixth production unit (334 MW) and the ecological plant (66.5 MW).